Close

    Works

    Building Progress Report

    Work of permanent building of KV Amarkot started on 28.02.2023 and according to monthly progress report of sept. 2024, 85 % of work completed till sept. 2024. According to monthly progress report presented by CPWD work of new building will be completed by last week of December 2024.